NIeT No. WBREDA/NIeT-02/18-19 Dated: 06-06-18

NIeT for “Operation & Maintenance of 2MW Wind Farm Project including HT OH lines (under WBREDA jurisdiction) , transformers, switchgear and other associated installations (Civil, Electrical & Mechanical) on ‘as is where is basis’ to keep the Wind Farm Project operational at Freserganj, Namkhana Block, District of 24 Parganas (South), West Bengal for a period of one year.”

To see the complete NIeT



Recent Development
  • The power demand in Sagar Island is, at present, met from Solar PV Power of aggregate capacity about 250 kW and from a diesel generator power system of capacity 400 kW. The total number of consumer in Sagar Island is to the tune of 1500 now.

    However, there are a large number of prospective consumers, who are awaiting for electric power.Under such circumstances,WBREDA has decided to set up a Wind-Diesel Hybrid power Plant of capacity 500 kW to cater the need of the Island people. [ more ]